Case Study2 min readDouglas Swinbanks

Flood and Surface Water Expertise Helps Deliver 24MW BESS Planning Consent in Sensitive Green Belt Site

Aegaea is pleased to have supported the successful planning approval of a 24MW Battery Energy Storage System (BESS) at Parkhouse Road, Barrhead. The project received unanimous backing from Glasgow City Council’s Planning Committee following a positive discussion highlighting the development as “well designed”, “quality” and reflective of the Council’s commitment to achieving Net Zero. Our role focused on managing flood risk and surface water drainage in what was a sensitive and technically challenging location.
Flood and Surface Water Expertise Helps Deliver 24MW BESS Planning Consent in Sensitive Green Belt Site

Project in brief

Committee resolution

Parkhouse Road, BarrheadA 24MW Battery Energy Storage System in the Green Belt

The question
Show the site would stay safe from flooding next to the Aurs Burn and not increase flood risk elsewhere.
Our work
Hydraulic modelling of the Aurs Burn, a flood risk assessment and a surface water drainage strategy.
Reported outcome
Planning Committee granted permission in June 2025, subject to a Section 75 Agreement. Construction is not recorded in this account.
On this page

Project Overview

The site sits within the Green Belt and forms part of the setting of the Dams to Darnley Country Park. It is also located adjacent to land with a known susceptibility to flooding, including the Aurs Burn watercourse.

As a result, flood risk and drainage were key issues throughout the determination process. It was essential to provide clear evidence that the development would remain safe from flooding and would not increase flood risk elsewhere.

Concrete culvert under a grassy embankment with a shallow stream flowing into the tunnel, surrounded by a wooden fence and rural landscape
Concrete culvert under a grassy embankment with a shallow stream flowing into the tunnel, surrounded by a wooden fence and rural landscape

Aegaea’s Approach

Aegaea was appointed to deliver a full flood risk and drainage strategy for the site. This included:

Our detailed modelling demonstrated that the site could accommodate the development safely, with no adverse impacts on flood risk to third parties. The proposed drainage measures ensured compliance with National Planning Framework 4 (NPF4) and supported the wider environmental objectives of the scheme.

Thanks to our extensive experience working within the Glasgow City Council area, we were able to identify and comply with Glasgow’s specific flood risk policies for Strategic Infrastructure. We also ensured appropriate consultation with Scottish Water regarding exclusion zones and easements related to their below-ground high-pressure supply assets.

Aegaea’s ongoing involvement in Essential Infrastructure projects, along with our expertise in low-carbon and zero-emission technologies, gave us a significant advantage in progressing this development.

Flood risk map showing site development boundaries, 1D model river sections, and 1000-year climate change flood depths in blue shades near Cowan Park
Flood risk map showing site development boundaries, 1D model river sections, and 1000-year climate change flood depths in blue shades near Cowan Park
Small woodland stream bordered by dense green foliage and overhanging trees on an early autumn day.
Small woodland stream bordered by dense green foliage and overhanging trees on an early autumn day.

The Outcome ✅

Planning permission was granted (subject to a Section 75 Agreement) at the June 2025 Planning Committee meeting. The outcome is particularly significant given the green belt location, flood sensitivity, and local environmental designations.

Aegaea’s input played a vital role in helping to resolve flood and drainage concerns, providing the confidence needed by consultees and decision-makers to support the scheme.

Written and reviewed by

Douglas Swinbanks

Principal Flood Risk and Drainage Engineer, Scotland · MEng (Hons) MCIWEM

I am a Member of the Chartered Institution of Water and Environmental Management (CIWEM), a Principal Flood Risk Engineer and Hydrologist based in Edinburgh, and I lead Aegaea's Scotland branch.

View profile →LinkedIn ↗

↑ Back to top

Case studies

Talk to us about your project

If this raises questions about your own site, we can help you work through them. Share your plans and any comments from the council, and we’ll send a free, no-obligation quote.

Newsletter

Stay ahead of flood risk and planning changes

  • Policy and flood map changes, explained in plain English
  • Practical guidance for your next planning application
  • New projects and lessons from our consultants

No spam. Unsubscribe any time. By signing up, you agree to receive our newsletter and occasional updates. See our privacy policy for how we use your data.

Read the latest update →

Preview: signup not connected yet.